Sarawak 500 KV Backbone Transmission Line Project

Advisory services for design review (part I) and construction supervision, contract management and QA/completion management (part II) for four transmission line construction contracts, i.e. three 500 kV double circuit lines totalling 511 km, and one 275 kV double circuit line 55 km.

Project name

Sarawak 500kV HVAC Transmission Backbone Project

Client

Sarawak Energy Berhad (SEB)

Location

Asia

Time span

2013 to 2018

Assignment

Advisory services for design review (part I) and construction supervision, contract management and QA/completion management (part II) for four transmission line construction contracts, i.e. three 500 kV double circuit lines totalling 511 km, and one 275 kV double circuit line 55 km.

Solution

Norconsult performed the following services; Part I: • The design tasks comprise detailed design analyses of 17 new tower types using PLS Tower/Staad Pro including full scale prototype testing of 6 tower types, detailed review of tower spotting and tower/span capacities / optimization using PLS CADD, detailed design review and full scale tests of foundations including piling, soil investigations and slope stability analyses, detailed design review of all conductors, optical ground wires, insulator strings, hardware, fittings etc. including factory acceptance tests (FAT). Part II • Advisory services to Employer on project management and contract management of construction contracts. • Tower factory manufacturing supervision in association with Bureau Veritas (Shanghai) • Advisory services to Employer on construction supervision. • Advisory services to Employer on QA and completion management (CMS system integration).

  • Geir Einar Nesgård

    Seniorrådgiver

  • Contact us

    Interdisciplinary collaboration